EXPO – Trigeneration

Belgrade, Serbia

EXPO – Trigeneration
Voltec d.o.o., for a project contracted by its parent company Log Design d.o.o., manufactured and delivered 59 panels of Siemens SIVACON S8 withdrawable switchgear.
The switchgear was delivered in mid-September 2025.

General information:
  • Construction of a trigeneration plant for supplying heating, cooling and electrical energy to the facility within the PPPPN National Football Stadium project
  • Investor: JKP “Beogradske Elektrane” Belgrade and the Ministry of Finance

Description:
  • Siemens SIVACON S8 MCC switchgear in accordance with SRPS IEC 61439-1/2
  • A total of 59 panels arranged into 8 MCCs
  • 3 MCCs rated at 2500 A
  • 2 MCCs rated at 1600 A
  • 3 MCCs rated at 1280 A